| Code | Work | Quantity |
|---|---|---|
| 01 | Sanding, priming and protective preparation | 1 set |
| 02 | Entrance area ceilings and walls | 50 m² |
| 03 | Repair and painting behind removed radiators | 23 pcs |
| 04 | Floor protection with film and paper | 1 set |
| 05 | Transport | 1 |
| 06 | Final cleaning | 1 |







Damaged wall areas were sanded, locally rebuilt, primed and prepared for a uniform final coating. Floors and adjacent surfaces remained protected throughout the works.










The shared entrance and elevator areas received a clean, consistent finish. Former radiator recesses and local wall damage were integrated into the existing interior surfaces.