RAMERK Project Manuals

RPM-002

Project Planning

How House of RAMERK turns an idea into a manageable project before work begins.

Collection · Project ManualsAuthor · RAMERKStatus · First EditionLanguage · EN / RU
Open the BookScroll to begin
Chapter 001

Purpose of Planning

A plan is not meant to predict everything. It is meant to make uncertainty manageable.

RPM-002 establishes a consistent process for preparing a House of RAMERK project before physical work begins.

Chapter 002

Project Definition

A project must have clear boundaries.

What is being created.
Who it is being created for.
Which outcomes are considered complete.
What is excluded from the current scope.
Chapter 003

Information Required

Good planning begins with complete baseline information.

Drawings, measurements, photographs, technical conditions, existing documents, client requirements, and site constraints are collected.

Chapter 004

Scope of Work

The scope of work must be described so that the client, craftsperson, and engineer understand it in the same way.

Each section defines the outcome, boundaries, dependencies, assumptions, and required approvals.

Chapter 005

Work Breakdown

A large project becomes manageable when it is divided into clear parts.

01

Phase

A major project stage.

02

Work Package

A complete package of work with an assigned owner and defined outcome.

03

Task

A specific action that can be verified.

Chapter 006

Sequence & Dependencies

Work must follow the logic of the construction, not the convenience of the calendar.

Dependencies between design, procurement, concealed works, inspections, and finishing operations are defined.

Chapter 007

Schedule

A schedule is not a single date. It is a system of interconnected commitments.

The programme includes preparation, approvals, procurement, execution, inspections, corrections, and handover.

Chapter 008

Budget Framework

A budget must show not only the total, but also how it was formed.

LayerMeaning
Base ScopeThe agreed scope of work.
AllowancesItems to be confirmed after selections are made.
ContingencyA contingency for justified unknowns.
ChangesChanges approved separately.
Chapter 009

Resources & Responsibilities

Every task must have an owner.

Responsibility is assigned for design, procurement, execution, quality control, approvals, and client communication.

Chapter 010

Procurement

Procurement becomes part of the project long before a material arrives on site.

For critical materials, the specification, order deadline, manufacturer confirmation, storage conditions, and incoming inspection are recorded.

Chapter 011

Risk Register

A risk no one discusses is still a risk.

Technical unknowns.
Dependence on weather and seasonality.
Long lead times.
Approvals and permits.
Third-party works.
Chapter 012

Quality Plan

Quality control is designed before work begins.

Inspection points, acceptance criteria, concealed-works records, required photographs, and handover documents are defined.

Chapter 013

Change Control

A change must not disappear into a conversation.

Every change is described, assessed for cost and time, approved, and only then incorporated into the project.

Chapter 014

Readiness to Start

Work begins when the project is ready — not when waiting has become inconvenient.

Start Gate

The scope is agreed, key decisions have been made, documents received, materials available, risks understood, and responsible persons appointed.

Chapter 015

The Planning Promise

We plan so that craftsmanship is protected from confusion, and trust is protected from surprise.

RPM-002

Project Planning · RAMERK Project Manuals · First Edition